Hidden Hammocks Estates Homeowners
Association BOARD OF DIRECTORS MEETING Integrity Property Management Co. Present: Tom Base – President/Treasurer Scott
Matchunis
– Vice President Tom
Toth
– Secretary Dave
Aronson – Director at
Large Mike
Whittle – Integrity
Property Mgmt.
The
minutes of the April
9th meeting
were approved 4/4 One homeowner was present
requesting an aluminum
perimeter fence. Property Management:
̃
The
Treasurer’s Report
̃
Cash on Hand
$42,988 ($6k
prepays included)
̃
Road Reserve
$46,537
̃
Homeowners past due assessments 12 $8,749
̃
On budget for regular operational expenses. Possible over budget
items: new security
company, architectural
fees & gate house
replacement; new front
gates; replace pavers
at the front entrance,
painting sprinkler pipes,
violation compliance
legal fees, maintaining
foreclosed properties,
etc Old Business
̃
For the gate attendants, the post supervisor should attend
the HHE BoD
meetings from now on
and give a status report.
Pursuit of a new security
company was tabled for
three months until the
direction of the ’08
budget is clearer.
̃
For the new mailboxes, distribute a reminder letter and order
form May 1st.
Follow up should include
a certified letter of
a special assessment
of $408 on May 12th
and a notice of intent
to send to collection
by June 2nd.
A detailed review is
needed of how many orders
have been placed.
̃
For the new gate house, discussions with Peter, the architect,
included:
o
Peter will meet
with the Coral Springs
Planning and Zoning
to review the plans
o
Demolition of
the old gate house is
estimated at $5k
o
Peter selects
the fine details of
tiles, windows, and
ornamental. A homeowner
will be consulted for
the final color selection.
o
The detailed
architectural design
will be held off until
given the go-ahead by
the BoD.
o
Landscaping design
will be by TopBranch.
o
The gate house
project cost is ball-parked
at $150-$200/squarefoot
for 10’ by 20’ plus
pavers, landscaping,
and gates.
o
Peter needs a
site survey.
o
The garbage was
proposed to be put underground
in the rear of the gatehouse.
o
HHE owes Peter
some portion of his
$6,200 fee.
o
Relocating the
gate house to the west
was proposed to allow
a more elegant, covered
entry.
o
The new gate
house was tabled for
three months until the
direction of the ’08
budget is clearer.
̃
For the exposed homeowner’s sprinkler pump pipes, painting
was tabled for three
months.
̃
For the uncertain future direction of the ’08 budget, 3 of
4 approved tabling the
new budget projects
for three months including
new security and new
gate house expenditures.
̃
For the lightposts, IPM demo’d the lightpost and fixture